The CNRL Extraction Plant consists of two (2) primary separation cells, flotation cells, twenty (20) pipe rack modules, hot water facility, electrical substation, and an emergency dump sump.
JV Driver was involved in this project from the early stages of development providing constructability support, labour strategies and construction services. Our role was general contractor, providing civil, structural, piping and mechanical services. We also provided the off-site fabrication and module assembly for this project. JV Driver's scope included 700,000 craft man-hours.
Having been involved with the entire scope of work, JV Driver was engaged for the entire four (4) year life of hte project. During this time, there were no changes in the productivity units. To add to this success, JV Driver was the first to turn over a silo for commissioning, and did so without any re-work and a weld repair of less than 1%.
This project was completed on time and LTA Free!